Construction information

 

Minismising construction impact

We recognise the need for the works to be carried out in a manner that limits the day-to-day impact on our neighbours. To help achieve this, a series measures are proposed, including:

 

  • Considered timing and routes for construction vehicles, ensuring safe access and minimum disruption to the local community.
  • Retaining full access for deliveries and collections to and from our neighbours.
  • Continuous monitoring of noise, dust and vibration levels.
  • Erection of scaffolding and safety hoarding around the sites.
  • Regular communications from the project team to ensure the local community are fully informed of upcoming works.

Site activity: Monday 23rd February – Friday 6th March

40 Pelham Street

Works happening in the refurbished building:

  • Ongoing electrical and mechanical works.
  • Internal fit out continues.

Works happening in the new building:

    • Continue zinc roof carpentry works, expected to be completed late-March.
    • Continue perimeter brickwork ongoing until April.
    • Commence installation of timber cladding.
    • Continue installation of basement tanking expected to be completed by the end of February.
    • Ongoing electrical and mechanical works.

    80 Pelham Street

    • Ongoing installation of steel beams.
    • Continued pouring of basement liner walls with most of the upper basement slab complete by the end of February.
    • Permanent substation works continuing expected to be complete by mid March.
    • Commence removal of the logistics slab from 24th February expected to take around a week. Crompton Court residents may notice some noise.
    • Periodic concrete breaking along Pelham Street to remove temporary works, with short periods of noise during agreed high impact hours.

    Working hours

    Both sites will be adhering to the core working hours agreed with RBKC, which are:

    Monday to Friday: 8am-6pm

    Saturday, Sunday and Bank Holidays: No noisy works without prior approval from RBKC

    Deliveries: 9:30am-4:30pm

    Managing traffic and deliveries

    A one-way system is in place along Pelham Street to help facilitate an on-street loading bay for construction vehicles. The system is in operation from Monday morning to Friday afternoon and the street reverts to two-way traffic at the weekend.

    The diversion route includes:

    • One-way traffic along Pelham Street travelling from South Kensington Station to Brompton Road (shown in blue on the map).
    • No entry to Pelham Street from Brompton Road – vehicles are diverted north to the A4 (shown in green on the map).
    • Buses using Brompton Road avoid Pelham Street and instead turn right onto Sydney Place (shown in orange on the map).

    There is signage in key locations to direct traffic, which clearly indicates where access is reserved for residents only.

    Road diversion map

    40 - 63 Pelham Street
    Privacy Overview

    This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.