Construction information

 

Minismising construction impact

We recognise the need for the works to be carried out in a manner that limits the day-to-day impact on our neighbours. To help achieve this, a series measures are proposed, including:

 

  • Considered timing and routes for construction vehicles, ensuring safe access and minimum disruption to the local community.
  • Retaining full access for deliveries and collections to and from our neighbours.
  • Continuous monitoring of noise, dust and vibration levels.
  • Erection of scaffolding and safety hoarding around the sites.
  • Regular communications from the project team to ensure the local community are fully informed of upcoming works.

Site activity: Monday 18th May – Friday 29th May

40 Pelham Street

Works happening in the refurbished building:

  • Continue internal fit out and decorating works.
  • Continue mechanical and electrical installations.

Works happening in the new building:

  • Continue installation of the external timber cladding.
  • Continue mechanical installations, including fan units.
  • Installation of raised access flooring ahead of door installation and final finishes.
  • Complete removal of scaffolding expected by 26th May.
  • Installation of the new stairs expected from 29th May.

Works happening in the courtyard:

  • Continue construction of the new garden wall.
  • Begin removing office cabins.

80 Pelham Street

  • Complete installation of the ground floor slab.
  • Complete installation of steel beams and columns at ground floor level.
  • Complete installation of precast stairs.
  • Final construction work of the internal floor slab at level six.
  • Removal of the concrete pile in the basement.
  • Connection of drainage pipes in the basement.

Site closure Spring Bank Holiday

Both sites will be closed from 6pm on Friday 22nd May and will reopen at 8am on Tuesday 26th May. During the closures, 24/7 security monitoring will be in place and Pelham Street will be open to two-way traffic.

Working hours

Both sites will be adhering to the core working hours agreed with RBKC, which are:

Monday to Friday: 8am-6pm

Saturday, Sunday and Bank Holidays: No noisy works without prior approval from RBKC

Deliveries: 9:30am-4:30pm

Managing traffic and deliveries

A one-way system is in place along Pelham Street to help facilitate an on-street loading bay for construction vehicles. The system is in operation from Monday morning to Friday afternoon and the street reverts to two-way traffic at the weekend.

The diversion route includes:

  • One-way traffic along Pelham Street travelling from South Kensington Station to Brompton Road (shown in blue on the map).
  • No entry to Pelham Street from Brompton Road – vehicles are diverted north to the A4 (shown in green on the map).
  • Buses using Brompton Road avoid Pelham Street and instead turn right onto Sydney Place (shown in orange on the map).

There is signage in key locations to direct traffic, which clearly indicates where access is reserved for residents only.

Road diversion map

40 - 63 Pelham Street
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.