Construction information
Minismising construction impact
We recognise the need for the works to be carried out in a manner that limits the day-to-day impact on our neighbours. To help achieve this, a series measures are proposed, including:
- Considered timing and routes for construction vehicles, ensuring safe access and minimum disruption to the local community.
- Retaining full access for deliveries and collections to and from our neighbours.
- Continuous monitoring of noise, dust and vibration levels.
- Erection of scaffolding and safety hoarding around the sites.
- Regular communications from the project team to ensure the local community are fully informed of upcoming works.
Site activity: Monday 24th August – Friday 4th September
40 Pelham Street
Works happening in the refurbished building:
- Continue internal finishes, including ongoing painting and decorating.
- Remove the temporary safety rail used for roof access.
- Installation of new railings and gates along Pelham Street.
Works happening in the new building:
- Continue internal finishes.
- Begin installation of the emergency access staircase from the middle of next week.
Works happening in the courtyard:
- Removal of scaffolding.
- Complete initial works to the party wall by the middle of next week.
- Commence landscaping works in early September.
80 Pelham Street
- Installation of the reception area expected to be completed by late September.
- Continuation of blockwork in the basement.
- Pouring the second floor concrete slab.
Working hours
Both sites will be adhering to the core working hours agreed with RBKC, which are:
Monday to Friday: 8am-6pm
Saturday, Sunday and Bank Holidays: No noisy works without prior approval from RBKC
Deliveries: 9:30am-4:30pm
Site closure Summer Bank Holiday
Both sites will be closed from 6pm on Friday 28th August and will reopen at 8am on Tuesday 1st September. During the closures, 24/7 security monitoring will be in place and Pelham Street will be open to two-way traffic.
Managing traffic and deliveries
A one-way system is in place along Pelham Street to help facilitate an on-street loading bay for construction vehicles. The system is in operation from Monday morning to Friday afternoon and the street reverts to two-way traffic at the weekend.
The diversion route includes:
- One-way traffic along Pelham Street travelling from South Kensington Station to Brompton Road (shown in blue on the map).
- No entry to Pelham Street from Brompton Road – vehicles are diverted north to the A4 (shown in green on the map).
- Buses using Brompton Road avoid Pelham Street and instead turn right onto Sydney Place (shown in orange on the map).
There is signage in key locations to direct traffic, which clearly indicates where access is reserved for residents only.
Road diversion map